Capacity arriving — HBM4
schedule a named mechanism, not a conclusion
2 announced additions totalling 130 kwpm HBM DRAM wafer starts against a base of 395. Confidence-weighted, that is a 25% expansion. Arriving capacity relieves the scarcity the owner earns on.
The path
| node | effect |
|---|---|
| HBM4 | -0.25 |
| Advantest Corporation | +0.15 |
| Camtek Ltd. | +0.15 |
| Google TPU (Alphabet) | +0.15 |
| Lam Research Corporation | +0.15 |
| Micron Technology | +0.25 |
| Onto Innovation Inc. | +0.15 |
| Powertech Technology Inc. | +0.15 |
| Samsung Electronics | +0.25 |
coverage
Dated 2026-Q4. By confidence: 1 firm, 1 planned. Confidence weights the magnitude rather than filtering — a speculative addition is the part of the pipeline most likely to slip, and hiding it would make the schedule look firmer than it is.
Arguments about this mechanism
None yet. No thesis names this mechanism’s subject, which is a gap in the bank rather than a fact about the mechanism.