the-megawatt-is-the-unit-of-account · conviction medium · status open · horizon 2027-2029 · as of 2026-08-04
Series available as data/the-megawatt-is-the-unit-of-account.csv
51% if the 3 gates are independent, 75% if they move together. They are claims about one industry, so the truth is between and nobody can say where. Treat this as an ordering device rather than a calibrated probability — the ranking of premises is the information, not the level.
Weakest link: Interconnection queue throughput and withdrawal rate (MISO) at 0.75 — TIMING, not withdrawal rates. Large-load connection runs roughly 4 years nationally and about 7 in Northern Virginia, against datacenter COD of 18 mon
32% if the 3 gates are independent, 65% if they move together. They are claims about one industry, so the truth is between and nobody can say where. Treat this as an ordering device rather than a calibrated probability — the ranking of premises is the information, not the level.
Weakest link: Ai Capex Cycle — signal 2026-08-04 at 0.65 — Wells Fargo NVL72 BOM: Vera Rubin at $8.34M per rack against GB300 at $4.23M, a 97% increase. Per GW of IT power, $61,895M against $50,101M — only 24%
27% if the 3 gates are independent, 60% if they move together. They are claims about one industry, so the truth is between and nobody can say where. Treat this as an ordering device rather than a calibrated probability — the ranking of premises is the information, not the level.
Weakest link: Vertiv Holdings Co at 0.60 — The power-conversion chain is where a percentage point of end-to-end efficiency is recovered, and it is a named investable layer rather than an engine
6% if the 4 gates are independent, 32% if they move together. They are claims about one industry, so the truth is between and nobody can say where. Treat this as an ordering device rather than a calibrated probability — the ranking of premises is the information, not the level.
Weakest link: conclusion:the-megawatt-is-the-unit-of-account#2 at 0.32 — Same correction: entered at 0.65 against conclusion 2's composed 0.3185. A depreciation argument denominated in chips does not reach this conclusion a
AI capex is modelled per chip and per rack. Rising rack cost is inflation in the buildout, and depreciation schedules of 5-6 years are defensible because older accelerators cascade down to inference and batch work.
When grid interconnect is the binding input, the megawatt is the unit that is actually scarce and everything should be denominated in it. Per-GW capex is rising far slower than per-rack capex; a chip's economic life ends when its watts are worth more running newer silicon, which is shorter than its physical life; and a 3% power-delivery improvement is capex avoidance rather than an energy saving.
Consensus computes dollars per GPU and years of physical life. This computes dollars per megawatt and asks what the watts could otherwise be running. The two give opposite readings on Rubin's cost inflation and on whether the cascade defence for depreciation survives.
Grid interconnection queue position0.85 strongIt is a generation and storage queue; LBNL states large loads are in separate queues not covered by it, so the withdrawal statistic measured speculative GENERATORS abandoning projects and said nothing about a datacenter obtaining load service. The better evidence is more recent and points the same way: on 2026-06-18 FERC issued Section 206 show-cause orders against all six RTOs — MISO is Docket EL26-70 — preliminarily finding the tariff unjust and unreasonable precisely BECAUSE it lacks large-load interconnection provisions, for loads above 50 MW on lines above 69 kV. The strongest support for power access binding is that as of mid-2026 there was no functioning large-load tariff at all.
Interconnection queue throughput and withdrawal rate (MISO)0.75 strongLarge-load connection runs roughly 4 years nationally and about 7 in Northern Virginia, against datacenter COD of 18 months to 3 years — the mismatch IS the constraint. the ERCOT large-load queue is around 410 GW with 198 GW applied in Q1 2026 alone. NOTE ON INDEPENDENCE: this premise and the one above are close to the same proposition measured twice, so multiplying them understates the conjunction; the product rule assumes independence and these are not independent.
Heavy-duty gas turbine delivery slots0.80 strongBoth the primary route and the bypass are queued, and the queue is the only input in this chain with a multi-year lead time. That is what makes the megawatt scarce in a way the chip is not: silicon supply responds to price within a cycle and interconnection does not.
Ai Capex Cycle — signal 2026-08-040.65 moderatePer GW of IT power, $61,895M against $50,101M — only 24%. Memory rises from 26.6% to 30.8% of BOM; networking falls 11% per GW even as it rises 37% per rack.
NVIDIA Vera Rubin VR200 (R200)0.70 moderateThe rack costs more because it also consumes more power, which is exactly why the denominator matters.
Energy per token served (site level)0.70 moderateThis is the coefficient that converts a token forecast into a megawatt requirement.
THE SAME BILL OF MATERIALS SUPPORTS TWO OPPOSITE HEADLINES. Per rack, Rubin looks like brutal cost inflation at +97%. Per gigawatt it is +24%, because the rack also does far more work per unit of grid connection. Under a binding power constraint the second is the decision-relevant number and almost nobody quotes it. The networking line makes the point sharpest: up 37% per rack and DOWN 11% per gigawatt, which reverses the sign of the conclusion depending on denominator.
Package shoreline (perimeter and cross-section contention between power, memory and data)0.70 moderateThe engineering is usually justified on loss, and loss is not why it pays.
Multilayer ceramic capacitor (high-capacitance, AI server)0.65 moderateCollapsing the path from ~40mm to ~2mm removes most of it.
Vertiv Holdings Co0.60 moderateIf interconnect is fixed at 300 MW for three years — and it is, because queue positions are multi-year — then a 3% end-to-end power-delivery improvement is ~9 MW of compute that did not require a new facility. At roughly $10M per MW of AI-ready facility that is on the order of $90M of avoided capex, recurring, from a change that appears in no marketing deck. This is why power-delivery engineering is getting attention disproportionate to how dull it sounds.
conclusion:the-megawatt-is-the-unit-of-account#10.51 moderateThis entered at 0.80 while conclusion 1 composes 0.5100 — citing a 0.51 conclusion at 0.80 IS the restatement the annotation claimed to avoid, and it is the framework exempting itself from its own rule at the point the rule bites hardest. Chained legs now carry the referenced conclusion's output, enforced by tools/rigor.py.
conclusion:the-megawatt-is-the-unit-of-account#20.32 weakA depreciation argument denominated in chips does not reach this conclusion at all, but the dependency cannot be cited more confidently than the thing it depends on.
Assumed GPU useful life (depreciation schedule)0.60 moderateHyperscalers use 5-6 year schedules; Amazon shortened a subset to five while Meta extended in the same window, so the industry does not agree with itself.
CoreWeave, Inc.0.65 moderateTHE INVESTABLE CLAIM AND THE HONEST LIMIT TOGETHER. Under a binding grid constraint a chip's economic life ends when the watts it occupies are worth more running newer silicon, which is strictly shorter than its physical life — the cascade defence implicitly assumes the pre-2023 world where power was abundant. That makes the power framing tighter than the accounting framing. BUT TWO THINGS CUT THE OTHER WAY AND THIS DESK HOLDS BOTH: H100 rental stabilising at $2.85-3.50/hour after a ~70% fall is evidence of a functioning secondary market, and free cash flow is identical whichever schedule is used, so this is an earnings-presentation question rather than a solvency one UNLESS the accounting distortion is itself driving overinvestment. TREAT AS UNRESOLVED. The observable that settles it is cohort-level utilisation disclosure and whether older-vintage rental floors hold.
Pre-filled skeleton: the-megawatt-is-the-unit-of-account.md